Smart Deadline Predictor

Smart Deadline Predictor

Non-Working Dates (Holidays/Vacation)

How the Prediction Works

1. Calculate Net Workdays
The tool first calculates the total number of workdays needed:
Workdays = CEILING(Total Estimated Effort Hours / Work Hours per Day)
This ensures any partial day of work counts as a full workday towards the schedule.
2. Apply Buffer
If you provide a buffer percentage, it's added to the net workdays:
Workdays with Buffer = CEILING(Workdays * (1 + Buffer Percentage / 100))
3. Iterate from Start Date
The predictor then starts from your chosen 'Start Date' and counts forward, day by day.
4. Skip Non-Working Days
Each day is checked:
  • Is it a weekend? (Based on your 'Workdays per Week' selection: 5-day week skips Sat/Sun; 6-day week skips Sun).
  • Is it in your list of specified 'Non-Working Dates'?
If a day is a non-working day, it's skipped, and the tool moves to the next day.
5. Count Workdays
For every day that is identified as a working day, the 'Workdays with Buffer' count is decremented.
6. Predict Deadline
The date on which the 'Workdays with Buffer' count reaches zero is your predicted deadline.
Assumptions
  • Work effort is distributed evenly at the specified 'Work Hours per Day'.
  • The 'Work Hours per Day' are consistently achieved on each working day.
  • Non-working dates provided are accurate.